S No |
Name of Project |
Location |
Amount |
Status |
Remarks |
1 |
Green Lash protection wall |
Green Lash |
4 Crore |
Approved |
Work started |
2 |
ReshunGol Channelization |
Reshun |
5 Crore |
Approved |
Work started |
3 |
Green Lasht Pipeline |
Reshun |
|
Tendered |
|
4 |
Reshun Pipeline |
Reshun |
|
Tendered |
|
5 |
Reshun Pasture (Ghari) |
Reshun |
|
Approved |
ADP |
6 |
Reshune Power House Road |
Reshun |
|
Approved |
|
7 |
Ziat 4 Small projects |
Ziat |
|
Approved |
|
8 |
Koragh Bridge |
Koragh |
1 Crore |
Tendered |
|
9 |
Koragh 3 link roads |
Koragh |
|
Tendered |
|
10 |
KoraghPawasoon Road |
Koragh |
|
Approved |
Work started |
11 |
BooniMastuj road |
Koragh |
2 Crore |
Approved |
|
12 |
Charoon Pipeline |
Charun |
|
Tendered |
|
13 |
CharunOvir Road |
Charun |
|
Tendered |
|
14 |
Charun 3 link roads |
Charun |
|
Approved |
|
15 |
Govt Boys College Boundry wall |
KhandanBooni |
|
Approved |
|
16 |
Govt Boys College Classes Extensions |
KhandanBooni |
|
Approved |
Work Completed |
17 |
Junalikoch channelization |
Junalikoch |
|
Approved |
|
18 |
GGD College Hostel and Class rooms |
Junalikoch |
10 Crore |
Approved |
|
19 |
Bridge near GGDC |
Junalikoch |
3 Crore |
Approved |
Work Completed |
20 |
Gahli Stadium |
Booni |
1.5 Crore |
Approved |
Work started |
21 |
Booni RCC Bridge |
Booni |
7 Crore |
Approved |
Work started |
22 |
Booni Bridge to Guest House road |
Booni |
|
Tendered |
|
23 |
Bridge Mulgram |
Booni |
32 Lac |
Approved |
Work started |
24 |
THQ Hospital Category-C Upgradation |
Booni |
56 Crore |
Approved |
Work started |
25 |
Shipishon channelization |
Booni |
90 Lac |
Approved |
|
26 |
Booni channelization |
Booni |
1 Crore |
Approved |
|
27 |
BooniGol Road |
Booni |
|
Tendered |
|
28 |
Water Supply Phase 1-2-3 |
Booni |
70 Lac |
Tendered |
|
29 |
Computer Lab High Boys High School |
Booni |
|
Approved |
Work Started |
30 |
Reconstruction of Class rooms GGH School |
Booni |
2.5 Crore |
Approved |
Work Started |
31 |
Booni Ada to BooniLasht Road |
Booni |
87 Lac |
Approved |
Work Started |
32 |
7 link roads |
Booni |
|
Tendered |
Work started |
33 |
Awi Pipeline |
Awi |
|
Approved |
|
34 |
2 Bridges Awi-Domadomi |
Awi |
|
Approved |
|
35 |
2 link roads |
Awi |
|
Approved |
|
36 |
Awi Last to Domadomi road |
Awi |
3 Crore |
Approved |
|
37 |
Parwak State Road |
Parwak |
|
Tendered |
|
38 |
Parwak Bridge |
Parwak |
|
Tendered |
|
39 |
Pipeline ParwakBala |
Parwak |
|
Tendered |
|
40 |
3 link roads |
Parwak |
|
Tendered |
|
41 |
NisoreGol water channel |
Nisorgol |
|
Tendered |
|
42 |
NisorGol Road |
Nisorgole |
|
Tendered |
|
43 |
GPS ParwakBalla |
Parwak |
|
Approved |
|
44 |
MastujKhas Pipeline |
Mastuj |
|
Tendered |
|
45 |
Waiting room in Mastuj Bazar Bus Ada |
Mastuj |
|
Approved |
Work Completed |
46 |
Mastuj Road Bazar |
Mastuj |
80 Lac |
Approved |
|
47 |
PasumGol-Hazrad Abad Protection wall |
Mastuj |
|
Approved |
Work started |
48 |
Bay Pass road Ghuro-Kohz-Istuch |
Brep Area |
|
Approved |
|
49 |
Harchine Pipeline |
Laspur |
|
Approved |
|
50 |
Electricity Poles Laspure area |
Laspure |
|
Approved |
|
51 |
8 small projects |
Laspure |
|
Approved |
|
52 |
3 Projects |
Chunje |
|
Approved |
|
53 |
Parkosap Bridge repairing |
Parkosup |
|
Tendered |
|
54 |
Parkosup Pipeline. |
Parkusap |
|
Tendered |
|
55 |
GhoruPaidel Bridge |
Ghuro |
|
Approved |
Work Completed |
56 |
Brep Pipeline |
Brep |
|
Tendered |
|
57 |
Higher Secondary School upgradation |
Brep |
|
Approved |
|
58 |
Kargin Protection Wall |
Kargine |
4.5 Million |
Approved |
Work started |
59 |
Kohz Road |
Kohz |
|
Tendered |
|
60 |
Kohz channelization |
Kohz |
|
Approved |
Work Completed |
61 |
Kohz Pipeline |
Kohz |
|
Tendered |
|
62 |
31 Project Yarkhoon |
Yarkhoon |
|
Tendered |
|
63 |
Primary School Pahshk |
Pahshk |
|
Tendered |
|
64 |
Bang Pipeline |
Bang |
|
Tendered |
|
65 |
Birzoz Road and Pipeline |
Birzoz |
|
Approved |
|
66 |
Upper Yarkhon High School |
U.Yarkhon |
|
Approved |
Work started |
67 |
Bang Grain Godam |
Bang |
|
Approved |
|
68 |
Upper Yarkhon Water Supply 8 Projects |
Upper Yarkhon |
|
Tendered |
|
69 |
Baroghil Road |
Baroghil |
|
Approved |
|
70 |
Miscl small projects by Provincial Govt |
Upper Chitral |
500 Million |
Approved |
|
71 |
Lot Ovir.Higher Secondary School |
Lot Ovir |
|
Approved |
Work started |
72 |
Pipeline 3 projects |
Lot Ovir |
|
Tendered |
|
73 |
Primary School |
Lot Ovir |
|
Approved |
Work started |
74 |
Lot Ovir Road |
Lot Ovir |
6 Million |
Approved |
Work Completed |
75 |
Lone Pipeline |
Lone |
4 Crore |
Tendered |
|
76 |
Lone School Upgradation |
Lone |
|
|
|
77 |
Kosht -Gohkir-Lone Truck able Road |
Kosht, Gohkir, Lone |
|
Approved |
ADP |
78 |
Kosht Pipeline |
Kosht |
3.Crore |
Approved |
Work Started |
79 |
KoshtRcc Bridge |
Kosht |
5 Crore |
Approved |
|
80 |
Kosht Grain Godams |
Kosht |
|
Approved |
|
81 |
Gohkir Grain Godams |
Gohkir |
|
|
|
82 |
Muzgol Canalization |
Muzgol |
|
Approved |
Work Completed |
83 |
Muzgol Bridge |
Muzgol |
|
Approved |
Work Completed |
84 |
Muzgol Medal School |
Muzgol |
|
Approved |
Work started |
85 |
3 KM Road Mulkhow |
Mulkhow |
|
Approved |
|
86 |
Sakht Road |
Sakht |
|
Approved |
ADP |
87 |
5 Pipeline Nogram to Sakht |
Sakht |
|
Tendered |
|
88 |
Warijun to Terich Road |
Warijun , Tarich |
|
Tendered |
ADP |
89 |
Koshum 3 projects and Pipeline |
Koshum |
|
Approved |
|
90 |
Zazdi Pipeline |
Zazdi |
1Crore |
Approved |
Cash Released |
91 |
Madak Pipeline |
Madak |
4 Crore |
Approved |
|
92 |
Nishko |
Nishko |
5 Crore |
Approved |
Work Started |
93 |
Higher Secondary School Nishko |
Nishko |
|
Approved |
Land is purchased |
94 |
5 Projects in Terich |
Trich |
|
Tendered |
|
95 |
Terich Grain Godam |
Trich |
|
Approved |
|
96 |
GGHS Tarich |
Trich |
|
Approved |
Near to Complete |
97 |
Istaro Channel Work |
Istaro |
|
Tendered |
|
98 |
Istaro Pipeline |
Istaro |
|
Tendered |
|
99 |
Warkop Pipeline |
Warkop |
|
Tendered |
|
100 |
Shagram Pipeline |
Shagram |
|
Approved |
|
101 |
Melp 2 Pipeline |
Melp |
|
Tendered |
|
102 |
Melp Road |
Melp |
5. Million |
Approved |
Work Started |
103 |
Shagram Channel Work , |
Shagram |
|
Approved |
|
104 |
Shagram 2 Link Roads |
Shagram |
|
Approved |
|
105 |
Shotkhar Pipeline |
Shotkhar |
|
Approved |
|
106 |
Shotkhar Link Road |
Shotkhar |
|
Approved |
|
107 |
Rayin water supply |
Rayin |
|
Approved |
|
108 |
Yekhdiz Road |
Yekhdiz |
|
Approved |
|
109 |
Washich Pipeline |
Washich |
|
Approved |
|
110 |
Washich Middle School |
Washich |
|
Approved |
Work Completed |
111 |
Washich Link Road |
Washich |
|
Approved |
Work started |
112 |
Zang Pipeline |
Zanglasht |
|
Approved |
Work Started |
113 |
Kosht U.C 5 Projects |
Kosht |
|
Tendered |
|
114 |
Upper Kosht Road |
Kosht |
50 lac |
Tendered |
|
115 |
Ujnu Road |
Ujnu |
|
Tendered |
Work Started |
116 |
Ujnu Pipeline |
Ujnu |
|
Approved |
|
117 |
ZangLasht to Ujnu Bridge |
Zanglasht |
|
Approved |
Work started |
118 |
ZangLasht to Ujnu Road |
Zanglasht |
|
Approved |
|
119 |
Rech GGHS |
Rech |
|
Approved |
Work Started |
120 |
Higher Secondary School |
Rech |
|
Approved |
|
121 |
Rech Grain Godam |
Rech |
|
Approved |
|
122 |
Upper Primary School |
Upper Rech |
|
Tendered |
|
123 |
3 Small Bridges |
Upper Rech |
|
Approved |
Work Completed |
124 |
4 Small Projects |
Upper Rech |
|
Tendered |
|
125 |
All People works program dispensaries upgraded |
Upper Chitral |
|
Approved |
Work Started |
126 |
66 Cell point Grain Godam reconstruction |
Upper Chitral |
|
Approved |
|